Project of human resource training, containing the successive activities with their time
Table : Things To be Done for Bread and Biscuit Factory
| |||||
Step
|
Step Names
|
Predecessors
|
Time (Days)
| ||
1
|
Identifying the training needs
|
3 Days
| |||
2
|
Establishing the training participants
|
1
|
4 Days
| ||
3
|
Establishing the training objectives
|
1
|
4 Days
| ||
4
|
Planning the training tematical content
|
3
|
4 Days
| ||
5
|
Establishing the training teachers
|
1
|
1 Day
| ||
6
|
Training completing methods
|
3
|
5 Days
| ||
7
|
Program implementation
|
2
|
4
|
5 Days
| |
8
|
Partial evaluation
|
7
|
1 Day
| ||
9
|
Logistics insurance
|
6
|
7
|
2 Days
| |
10
|
Appreciating and evaluation of the
training results
|
8
|
1 Day
| ||
TOTAL =
| |||||