Project of human resource training, containing the successive activities with their time
Table : Things To be Done for Bread and Biscuit Factory
| |||||
Step
|
Step Names
|
Predecessors
|
Time (Days)
| ||
1
|
Identifying the training needs
|
3 Days
| |||
2
|
Establishing the training participants
|
1
|
4 Days
| ||
3
|
Establishing the training objectives
|
1
|
4 Days
| ||
4
|
Planning the training tematical content
|
3
|
4 Days
| ||
5
|
Establishing the training teachers
|
1
|
1 Day
| ||
6
|
Training completing methods
|
3
|
5 Days
| ||
7
|
Program implementation
|
2
|
4
|
5 Days
| |
8
|
Partial evaluation
|
7
|
1 Day
| ||
9
|
Logistics insurance
|
6
|
7
|
2 Days
| |
10
|
Appreciating and evaluation of the
training results
|
8
|
1 Day
| ||
TOTAL =
| |||||
Useful Rules :
1. At first consider only those steps, having another step to it's right to reach the final destination.
(for example: Step 1, Step 2, Step 3, Step 4, Step 6, Step 7, Step 8)
2. Do not consider the time / duration of any step which does not have another step to it's right to reach the final destination. (for example: step 5 and step 9).
3. Find the longest / biggest path to reach the final step.
Here we found: Step 1 + Step 3 + Step 4 + Step 7 + Step 8 + Step 10
That means = 3 days + 4 days + 4 days + 5 days + 1 day + 1 day = 18 Days
However start date is 05 .07.2014 and the end date is 22.07.2014 = 18 Days
Hope you understand well. If you have any question, please ask it on the comment section at the bottom of each post.