Lecture 2 : PERT CHART

Project of human resource training, containing the successive activities with their time



Table : Things To be Done for  Bread and Biscuit Factory
Step
Step Names
Predecessors
Time (Days)
1
Identifying the training needs



3 Days
2
Establishing the training participants
1


4 Days
3
Establishing the training objectives
1


4 Days
4
Planning the training tematical content
3


4 Days
5
Establishing the training teachers
1


1 Day
6
Training completing methods
3


5 Days
7
Program implementation
2
4

5 Days
8
Partial evaluation
7


1 Day
9
Logistics insurance
6
7

2 Days
10
Appreciating and evaluation of the
training results
8


1 Day





TOTAL =



















find the PERT Chart from the link



Useful Rules :

1. At first consider only those steps, having another step to it's right to reach the final destination. 
(for example: Step 1, Step 2, Step 3, Step 4, Step 6, Step 7, Step 8)

2. Do not consider the time / duration of any step which does not have another step to it's right to reach the final destination. (for example: step 5 and step 9). 

3. Find the longest / biggest path to reach the final step. 
Here we found: Step 1 + Step 3 + Step 4 + Step 7 + Step 8 + Step 10 

That means    = 3 days + 4 days + 4 days + 5 days + 1 day + 1 day = 18 Days

However start date  is 05 .07.2014 and the end date is 22.07.2014 = 18 Days

Hope you understand well. If you have any question, please ask it on the comment section at the bottom of each post.