Wednesday, September 24, 2014

Final ExamSyllabus

Final Exam Syllabus:



3. GANTT Chart
4. Uses of GANTT Chart

6. Explanation of stages of System Development Life Cycle (SDLC) with proper example.
http://cabmba.blogspot.com/2014/06/system-development-life-cycle_27.html

7. E-Commerce and its areas with proper examples.
http://cabmba.blogspot.com/2014/09/lecture-4-ecommerce.html


9. Open Source Software (OSS) and their uses.
http://cabmba.blogspot.com/2014/09/lecture-6-open-source-software.html

From the above topics, you have been given 6 questions. You have to answer at least 4.

Best wishes for all.

Friday, July 18, 2014

Mid Term Syllabus

Mid Term Syllabus:

1. System Development Life Cycle (SDLC)

2. PERT Chart

3. GANTT Chart

4. Uses of GANTT Chart

5. Uses of PERT Chart

6. Explanation of stages of System Development Life Cycle (SDLC) with proper example.

From the above topics, you have been given five questions. You have to answer at least three.

Best wishes for all.

Friday, July 11, 2014

Lecture 3 : Gantt Chart

Project of human resource training, containing the successive activities with their time



Table : Things To be Done for  Bread and Biscuit Factory
Step
Step Names
Predecessors
Time (Days)
1
Identifying the training needs



3 Days
2
Establishing the training participants
1


4 Days
3
Establishing the training objectives
1


4 Days
4
Planning the training tematical content
3


4 Days
5
Establishing the training teachers
1


1 Day
6
Training completing methods
3


5 Days
7
Program implementation
2
4

5 Days
8
Partial evaluation
7


1 Day
9
Logistics insurance
6
7

2 Days
10
Appreciating and evaluation of the
training results
8


1 Day





TOTAL =



















find the GANTT rom the link



Friday, July 4, 2014

Lecture 2 : PERT CHART

Project of human resource training, containing the successive activities with their time



Table : Things To be Done for  Bread and Biscuit Factory
Step
Step Names
Predecessors
Time (Days)
1
Identifying the training needs



3 Days
2
Establishing the training participants
1


4 Days
3
Establishing the training objectives
1


4 Days
4
Planning the training tematical content
3


4 Days
5
Establishing the training teachers
1


1 Day
6
Training completing methods
3


5 Days
7
Program implementation
2
4

5 Days
8
Partial evaluation
7


1 Day
9
Logistics insurance
6
7

2 Days
10
Appreciating and evaluation of the
training results
8


1 Day





TOTAL =



















find the PERT Chart from the link



Useful Rules :

1. At first consider only those steps, having another step to it's right to reach the final destination. 
(for example: Step 1, Step 2, Step 3, Step 4, Step 6, Step 7, Step 8)

2. Do not consider the time / duration of any step which does not have another step to it's right to reach the final destination. (for example: step 5 and step 9). 

3. Find the longest / biggest path to reach the final step. 
Here we found: Step 1 + Step 3 + Step 4 + Step 7 + Step 8 + Step 10 

That means    = 3 days + 4 days + 4 days + 5 days + 1 day + 1 day = 18 Days

However start date  is 05 .07.2014 and the end date is 22.07.2014 = 18 Days

Hope you understand well. If you have any question, please ask it on the comment section at the bottom of each post.

Computer Application in Business (MBA)